Package D - 5kv Replacement Feeder 4

 

Work involves the installation of new 5kv cables, junctions, terminations, racks, switches and conduit. The following work was accomplished during summer and fall 2006 to allow for the re-feeding of switchgear.

Marston Hall –  re-feed from CIT substation

Gardner House – re-feed from Littlefield transformer

Hegeman Hall – replace 5kv switchgear

151 Thayer – re-feed loads from T78

In 2007 six transformers were replaced in the following buildings, Caswell, Hegeman, 151 Thayer, Littlefield, 37 Manning and Lincoln Field.

 