Package F - 5kv Replacement Feeders 2, 6 & 7

Package F replaces sections of Feeders 2, 6 & 7 along with 6 primary voltage transformers at the following locations; Faculty Club, Archibald, Poland, Mead and Wriston Quad. Also oil filled selectors and fused oil cutouts will be replaced. All work was completed in early 2008.

 