Rates currently in effect on active awards will be continued until the end of the current competitive segment. A competitive segment is a period of years approved by the sponsor at the time of the award. Existing projects will continue with the current rate as indicated in the award document until the end of the current award period or competitive segment.

Example:

Project Period: 07/01/2012 – 06/30/2022

Competitive segment: 07/01/2018 – 06/30/2022

Budget Period: 07/01/2019 – 06/30/2020

 

Facilities and Administrative Costs

Year 1

Year 2

Year 3

Year 4

Year 5

F&A Cost Rate 1

62.5%

62.5%

58.5%

59%

59.5%

F&A rate in Notice of Award for competitive segment: 62.5%

 

The 62.5% rate as specified in the notice of award for this competitive segment through 6/30/22.

 