Renovation Project
“The Stephen Robert ‘62 Campus Center will foster greater interaction among Brown’s extraordinary students, and exceptional faculty and staff. This will help achieve our plan for academic enrichment by building a shared sense of community."
- Stephen Robert '62
Thanks to the generosity of Stephen Robert '62 and several anonymous donors, the University will renovate Faunce House and create the new Stephen Robert ’62 Campus Center. Schwartz/Silver Architects have been selected to design the Center.
Become of fan of the Campus Center on Facebook to keep up on the latest information and images of the renovation.
Renovation Timeline
What's already done?
Part of the Center is already complete! The new Multipurpose Room opened on Monday, August 31, 2009. The room will host the temporary Blue Room Cafe and may be reserved during the evenings and on weekends for events and meetings by contacting University Scheduling. In addition to the Multipurpose Room, summer 2009 saw the restoration of three patios/terraces and limestone around the base of the building.
What's happening now?
Most of the building (except Stuart Theatre and the Blue Room/Multipurpose Room) is now closed. September/October 2009 work is primarily demolition, roof replacement, and exterior repair and restoration.
Planning Committee
A representative committee has been meeting to lead community input efforts and ensure student, faculty, and staff voices play a key role in the planning process.
- Gregory Abdo '10
- Victor Bartash '13, UCS Campus Life Committee
- Janet Cooper-Nelson, University Chaplain
- Eleanor "Ellie" Cutler '10
- Amie Darboe '10
- Wendy Edwards, Professor of Visual Arts
- Allison Fong, Ph.D. candidate in French
- Ricky Gresh, Senior Director for Student Engagement (Chair)
- Joelle Karlik '08, MD '11
- Margaret Klawunn, Vice-President for Campus Life & Student Services
- Christopher O'Neil, Staff Advisory Council and Production Manager for the Department of Theatre, Speech, and Dance
- Daniel Oviedo '11, Brown University Activities Council
- Anthony Evans, Ph.D. candidate in Psychology
- Gretchen Willis, Director of Brown Dining
Former members of the committee are: Russell Carey '91 MA '06, Jason Lambrese '06 MD '10, Robin McGill (Ph.D candidate in Classics), and Amy Tan '09.
John Cooke, Project Manager from the Department of Facilities is a resource to the committee.
Community Input
The participation of students, faculty, and staff in the life and activities of the Stephen Robert '62 Campus Center at Faunce House will be instrumental to its success -- not only after it opens but also throughout the planning process.
- Renovation Celebration on Wednesday, May 6, 2009
- Open Forum held Monday, April 27, 2009
- Spring 2008 Open Forums and Meetings
- Undergraduate Council of Students (February 13 and April 30),
- Medical School Student Senate (March 4),
- Religious Life Associates (April 1) and Religious Life communities (February 13),
- Graduate Student Council (March 5),
- Brown University Activities Council (April 30),
- Staff Advisory Committee,
- Subcommittee on Alcohol and Other Drugs,
- Third World Center,
- the Queer Alliance, and
- the administrative offices housed in J. Walter Wilson.
The Committee also provides occasional updates and reports to the Campus Life Advisory Board.
Questions, comments, and suggestions may be forwarded robertcampuscenter AT brown.edu.
In the News
- Unexpected Tuition Surplus Fast Tracks Faunce (BDH, October 10, 2009)
- Blue Room Opens New Digs (BDH, September 8, 2009)
- Summer 2009 construction coverage in article entitled Metcalf overhaul planned after new building scrapped (BDH, July 19, 2009)
- Faunce overhaul headlines summer construction (BDH, April 23, 2009)
- Article covering the 2/13/08 UCS meeting during which UCS and guests were invited to give input (BDH, February 14, 2008)
- Faunce House renovation to begin in summer 2009 (BDH, February 11, 2008). Please note two corrections: (1) construction is currently anticipated to begin summer 2009; however, this timetable may still change and (2) the Student Activities Office is not moving to J. Walter Wilson and is currently slated to be part of the Robert Campus Center.
- Schwartz/Silver Architects to Design Robert Campus Center (Brown News Office, February, 8, 2008)
- Planning for Campus Center to Begin this Fall (BDH, September 12, 2007)
- J. Walter Wilson to house student support services (BDH, March 22, 2007)
- This Time, For Real (BDH editorial, March 1, 2007)
- Changes to Faunce could come as soon as this summer (BDH, March 1, 2007). Please note that a correction is at the end of the article clarifying that any Faunce renovation would not begin until a later date.
- Corporation approves student center, elects new chancellor (BDH, February 26, 2007)
- Faunce House To Be Renovated as Stephen Robert Campus Center (Brown News Office, February 24, 2007)